MLC Convention
Approval of DMLC
- Issuance of DMLC Part Ⅰ
- Drawing-up of DMLC PartⅡ
- Application for approval of DMLC PartⅡ
- Approval of DMLC PartⅡ
DMLC Part I is a declaration which states the national requirements for implementation of MLC, 2006, and DMLC Part II is a declaration adopted by the shipowner to ensure compliance with the requirements on the DMLC Part I.
What does DMLC Part II declare?- 1. Identified measures for ongoing compliance with the national requirements between inspections
- 2. Identified proposed measures to ensure ongoing improvement
- 3. If national requirements require ongoing compliance, identify the responsibility of verification, record of action taken and the action to be taken when breach occurs
Issuance of (interim) Maritime Labour Certificate
- Application for MLC inspection
- MLC inspection
- Issuance of(interim) Maritime Labour Certficate
- 1. new ships on delivery;
- 2. when a ship changes flag; or
- 3. when a shipowner assumes responsibility for the operation of a ship which is new to that shipwoner
Notice: For interim MLC inspection, the ship should be manned in accordance with the Safe Manning Document. In addition, DMLC Part II should be submitted to the competent authority or RO for its approval.
Conditions of initial MLC inspection- 1. DMLC Part II of which review was completed by the competent authority or RO to be onboard the ship; and
- 2. Identified proposed measures to ensure ongoing improvement
- 3. If national requirements require ongoing compliance, identify the responsibility of verification, record of action taken and the action to be taken when breach occurs
In case of accoummodation facilities of new building
- Apply for approval of plans
- Approval of plans
- On secne inspection
Ships which has been constructed on or after the Convention enters into force
A ship shall be deemed to have been constructed on the date when its keel is laid or when it is at a similar stage of construction